The batching plant alternative for work spread across several sites
If concrete is wanted in three places this month and somewhere else next month, or on one site for only a few weeks, a fixed or semi-mobile batching plant is answering a question you are not asking. A plant is a decision about a piece of ground before it is a decision about concrete. It produces at one point on the map, the pour happens at another, and the distance between them is governed by a clock rather than by the plant's rating. Where that distance differs at every site it feeds, the plant is sited for the average and fails at the one furthest out. The alternative is not a smaller plant. It is to carry the loading, the proportioning and the mixing to the work on one chassis.
Source: reasoning. We hold no quotation, list or price band for a fixed or semi-mobile batching plant of any size, and no price for one appears anywhere on this site.
What a plant commits you to before it makes its first cubic metre
Seven conditions have to hold, and not one is the mixer people picture when they price a plant. A site you can hold for the length of the work. A power supply, or a generator sized for the mixer and the conveyors. Stockpile area for aggregate, with access good enough for tippers to keep it filled. A cement silo. Water. Somewhere for washout to settle. And a way of getting the concrete from where it is made to where it is poured. Each is a condition rather than a cost, and one that fails does not make the plant cheaper; it makes it idle. The last is the one most often left out of the comparison, and on scattered work it becomes the whole problem: the ready-mixed concrete specification itself tells a purchaser to consider the projected transportation time between the batch plant and the point of delivery.
Source: the seven conditions are stated as conditions rather than costs, because no price for a plant is held here. The note on projected transportation time between the batch plant and the point of delivery is the American ready-mixed concrete specification's own, reproduced in the appendix to the Californian placement-times notice cited in the next section, which is where we read it.
The haul radius is a term in your specification, not a constant
The binding limit on a fixed plant is rarely how much it can mix. It is how far the concrete can travel before it has to be in the form, and the clock starts when the mixing water meets the cement and aggregates rather than when the truck leaves the gate. The American ready-mixed concrete specification no longer states a number. In its 24d edition, clause 6.1.10 makes the limit from the start of mixing to the completion of discharge the purchaser's to state, falls back to the producer where he states none, and requires the time limit printed on the delivery ticket. Clause 6.1.9 puts the drum-revolution limit, which governs when discharge must begin, on the purchaser in the same way and with the same fallback to the producer. Some authorities have put a number back. California's health facilities authority requires discharge completed within one and a half hours and within 300 drum revolutions, of which no more than 100 may be mixing, and lets neither party waive either, though it sets out a documented procedure for unplanned delays.
What that does to a haul is arithmetic you can run on your own figures. Take a ninety-minute limit, the one California still imposes on the work it regulates and the one the specification carried until it was deleted. Assume ten minutes from water to the plant gate, thirty-five out, fifteen waiting at the site: sixty gone, thirty left for discharge and placement. Move the pour front ten kilometres further on at an assumed thirty kilometres an hour and the outbound leg grows by twenty minutes, so the window falls from thirty to ten. None of those four durations is measured. Substitute your own and the shape survives, because the allowance is fixed and the haul is not. On scattered work the leg does not grow once. It is a different number for every site, and the site at the far end of the radius runs out first.
Source: clauses 6.1.9 and 6.1.10 of the American ready-mixed concrete specification, 24d edition, reproduced verbatim in the appendix to California Department of Health Care Access and Information Policy Intent Notice 82, "Ready Mix Concrete/Grout Placement Times", effective 9 October 2025; the time limit, the 300-revolution and 100-mixing-revolution split, the no-waiver sentence and the start-of-clock definition are that notice's own policy section, read on 24 September 2026. Washington State's 2024 highway specifications set the same kind of limit differently again, at 320 revolutions combined and 45 minutes for concrete hauled in a non-agitating body, or 60 minutes at 70°F or below or with an approved retarder at minimum dosage. Both are declared regulatory text for American jurisdictions, and neither is asserted to govern your contract. The four durations in the worked example are assumptions, stated as such, and they measure nothing.
What the customs record says about this machine, counted our own way
The evidence here is our own: a read of the customs declarations on both sides of the record, done row by row. China declared 18,017 concrete-mixer vehicles exported under HS 8705.40 in 2024, worth USD 800.26 million, across 145 partner entries whose rows add back to the world row exactly. The seven largest destinations carry 9,523 units between them, 52.9 per cent of the total. The tail behind them is long and thin: 57 entries record fewer than ten units and account for 200 units in total, and three entries are residual groupings rather than countries at all. So a little over half of this trade moves through seven lines, and rank thirty took 108 units and rank ninety took eight, and the fifty-seven entries under ten units account for 200 machines between them.
The step that makes those figures usable is the one most published rankings skip. A single query returns the total row alongside every partial view of the same total — split by customs procedure, by mode of transport, by second partner — and nothing marks the duplicates as duplicates. Sum every row of the query for Peru's 2024 imports of this heading from China and you get 1,124 units against a correct 281: a ratio of exactly four on units and on value. Four other reporters inflate twofold and two more fourfold. Every figure above comes from the one row where all three breakdown keys sit at their totals value. Five of the twelve importing countries that filed for 2024 then turn out to carry a modelled unit count rather than a counted one, and they give themselves away: the quantities are not whole numbers, and three of the five divide out at USD 58,536 per unit while the other two land on USD 63,315. A shared divisor is not a shared market.
Source: UN Comtrade annual data for HS 8705.40, 2024 — China as reporting exporter on the export side, one reporter per country on the import side, every figure taken from the single row where customs procedure, mode of transport and second partner all sit at their totals value. The four-times ratio, the twofold and fourfold inflations and the per-unit divisors are arithmetic performed on those rows. Our compliance guide on how a customs table hands you the opposite answer works the same errors through in full, and our markets guide on where mixers shipped in 2024 carries the destination table. These are shipping declarations, and an export declaration records the destination stated to customs at the time of shipment rather than where a machine is put to work.
What we put in writing that the category does not
Six things go onto our pages that the trade generally leaves off, and every one is checkable against a page already live on this site. We publish the drum's geometric volume and the volume of mixed concrete that comes out as two separate numbers, and never derive one from the other: on the SLM-18, a 2,900 litre drum discharges 1.6 to 1.8 cubic metres a load. We say when a dimension's measuring position has not been established — ten of the sixteen self-loading mixers in our records carry overall dimensions, and on nine the plant gave figures without stating what position the machine stood in, so those widths stand and those heights are not offered as clearance figures. And we leave a cell blank rather than estimate it: one published model shows no discharge capacity, because two specification sheets disagree and a conflicting row does not render.
The other three are about what a specification may be attributed to. The cubic-metres-an-hour line exists on all six published model sheets, is empty on all six, and stays empty. Weighing is stated model by model rather than as a category feature: the electronic hydraulic weighing device is standard on one of the six, an option on four and on neither list on the sixth, and we say in writing that the option list runs line-wide, so an entry proves the device can be fitted to that line and nothing about how your machine was built. And we state the origin rule the way the agreement writes it: Form E is applied for by the exporter and an importer cannot open one, and where it was not issued at shipment, nor within three days of it, the ACFTA procedures say it shall still be issued at the exporter's request within twelve months of the shipment date, marked ISSUED RETROACTIVELY in Box 13.
Source: the model comparison table and the six published model sheets on this site's self-loading mixer page. The SLM-18 is the one model that passes our own publish gate, which is why it is the only model named with figures anywhere on this page and everything else is given at range level. Dimensions, discharge figures and equipment entries are as the plants declared them, counted across the sixteen self-loading mixers in our records; the five crawler dozers in the same records are a different category of machine and are counted nowhere on this page. The Form E wording is the ACFTA operational certification procedures, set out in full in our compliance guide on Form E.
The comparison, dimension by dimension, with the unknown cells left unknown
Six dimensions decide this, and we can put a sourced figure on four. The other two say so rather than answering.
| Dimension | Fixed plant and truck | Self-loading mixer |
|---|---|---|
| Access | The feeding vehicle may be up to 2.6 m wide, 10.5 m long and 3.8 m high and weigh 32 t fully loaded | 1.60–2.30 m wide across the ten of sixteen records carrying a width |
| Batching accuracy | Within 1 per cent of required mass on cementitious material at or above 30 per cent of scale capacity, and within 2 per cent on an individual aggregate load | No stated accuracy exists for any machine in our records. The cell stays empty rather than taking a plausible tolerance |
| Haul time | The window set out above, which the outbound run comes out of | The interval between water and discharge collapses to the machine's own cycle. No cycle time is held for any of the six published models |
| Minimum order | A commercial floor exists because the producer's cost floor is a truck movement rather than a cubic metre. No figure has been sourced for any destination market | No commercial floor, because there is no trip to pay for. The smallest discharge figure in our records is 1.0 m³ |
| Crew | A banksman is required to supervise the truck's movement and positioning, and where the truck cannot discharge into the works, transport must be provided to move the concrete to them | Loading, mixing, driving and discharging sit on one chassis with one cab |
| Movement | Re-sited between contracts | Re-sited between pours. Four of the six published models declare a top travel speed: 0–23 km/h on the SLM-18 and 0–36 km/h on three larger models |
Source: the truck envelope, the banksman requirement and the transport-to-the-works requirement are quoted as printed from the British Ready-Mixed Concrete Association and the Mineral Products Association, "Ready-Mixed Concrete – Practical guide for site personnel", June 2020 edition, sections 3.1 and 3.2, which state the envelope of the largest truck in general use there rather than of every truck. The batching tolerances are the American ready-mixed concrete specification's, as set out in a United States Nuclear Regulatory Commission training course on concrete technology and codes; no machine on this site has been shown to meet them, because no plant has given us a stated accuracy for any weighing device on any model. The three calculator pages were each opened and read on 24 September 2026; the refusal and its seven questions are the first page's own published guidance, and the three-cubic-yard minimum and the eight-to-ten-cubic-yard truck are the other two pages' own stated American figures, carried here with their market attached. Widths, discharge figures and travel speeds are as the plants declared them, counted across our sixteen self-loading mixer records. No minimum order or short-load fee has been sourced for any destination market. The charge below which a drum will not mix properly is recorded on none of the sixteen and is not estimated here, and no turning radius is recorded for any of them either, so the turn into a yard is a question these figures cannot answer.
Where a fixed plant is still the right answer, and what we cannot tell you
A plant wins when the demand sits still. If concrete is wanted continuously, from one location, for long enough to justify the installation, and there is ground and power for it, the fixed plant is the better machine and nothing above argues otherwise. It also wins where several pour fronts run at once, for reasons of arrangement rather than measurement: a plant can fill a second truck while the first is driving, and a single self-loading machine cannot load the next batch while discharging this one. It wins on paperwork too, wherever a specification demands proportioning certified per batch, batch tickets or mix designs that change between loads. And a third answer beats both and should be checked first: if a ready-mix supplier already sits inside your discharge window and can reach the pour inside it, buying concrete is simpler than owning anything.
Three gaps on our side belong in the body rather than in a footnote. There is no price here for either option: we hold no sourced figure for a plant, our own pricing is a commercial decision not yet taken, and a payback period built from two unsourced numbers would be the most useful-looking and least true thing on the page. There is no output figure of any kind — not cubic metres per hour, per day, loads per shift, nor fuel — because none has been supplied for any machine in our records, and a rate got by multiplying a discharge volume by an assumed cycle time is arithmetic wearing the clothes of a measurement. And the documents behind the discharge window above are American: no destination market's concrete code has been read for this page, so no national limit is stated anywhere on it.
Source: the parallel-versus-series contrast is reasoning about how the two arrangements work, and it is deliberately not written as a ratio, because no measured output exists on either side to make one. The weighing and discharge-window facts are those cited in the sections above. The output line on every published model sheet is empty and marked unverified, which is why no output figure appears; no price of any kind is published anywhere on this site.
Send a model and a port
There is nothing to sign up to here. Send a model number and a destination port, and what comes back is a written quotation: one landed figure to that port with the shipping mode written into it, the certificates your market requires named, and Form E applied for on our side, because an importer cannot open one. Where a specification you need is one we do not hold in writing, the answer says so rather than filling the column from a neighbouring machine — that carry-over is where a container booking goes wrong, and it is why several rows in our published range are blank. The customs heading is confirmed by your broker before the proforma, since this machine answers to both 8705.40 and 8474.31 and the heading used decides whether it arrives as a vehicle or as machinery.
Source: this section is our own procedure and introduces no figure. The two customs headings and the broker's role are set out in our compliance guide on which heading applies; the Form E application rule is the ACFTA procedures cited above. No price is posted on this site, because a landed figure is quoted against a named port and a named specification rather than published.